The Great Room has also been sheetrocked downstairs and it is really taking shape nicely.
Some of the ceilings in the downstairs have been completed, but there is still quite a bit left to do. This is where things get a little tricky because the schedule was to have all of the sheetrock, mud and detail done by today. Obviously our builder is running a bit behind.
In fact, the schedule calls for the floors to be installed this week. Instead, we found out on Tuesday that the wood floor for the upstairs hasn't even been ordered yet. (Yikes!) So we are at least a few weeks behind. We're not sure how this will translate to our move-in timetable, but hopefully we'll find out this week. Wish us luck!